April 7, 2017 – The following overnight closures and lane restrictions are scheduled next week to accommodate punch list items in connection with work on the Downtown Crossing.

Overnight closure scheduled Monday, April 10

  • Ramp from I-65 South to I-64 West

The closure is scheduled to begin around 9 p.m. and end by 5 a.m.

Overnight closure scheduled Monday, April 10 and Tuesday, April 11

  • Ramp from I-64 East to I-65 North/I-65 South

The closure is scheduled to begin around 9 p.m. and end by 5 a.m. each day.

Overnight closures scheduled Tuesday, April 11 and Wednesday, April 12

  • Ramp from I-65 North to I-71 North
  • Ramp from Story Avenue to I-64 West
  • One lane of ramp from I-65 North to I-64 East/I-71 North
  • I-64 East reduced to one lane from 3rd Street to I-71 North
  • One lane closed on the ramp from I-64 West/I-71 South to I-65 South
  • One lane closed on I-64 West near Story Avenue and Witherspoon Street

The closures are scheduled to begin around 7 p.m. and end by 5 a.m. each day.

Overnight closures scheduled Wednesday, April 12 and Thursday, April 13

  • Ramp from Court Avenue to I-65 South (Jeffersonville)
  • Ramp from 6th Street to I-65 South (Jeffersonville)
  • Three lanes of I-65 South from Market St. to Kennedy Bridge (Jeffersonville)

The closures are scheduled to begin around 9 p.m. and end by 5 a.m. each day.

Overnight closure scheduled Friday, April 14

  • Ramp from I-64 East to I-65 North/I-65 South

The closure is scheduled to begin around 9 p.m. and end by 5 a.m.

Signed detours are in place during full closures. The actual starting date and duration for the work may be adjusted if inclement weather or other unforeseen activities occur. Find more information about the Ohio River Bridges Project at www.kyinbridges.com.

Navigate traffic with KYTC, www.511.ky.gov, and Waze, www.waze.com.