Feb. 20, 2017 – The following overnight closures and lane restrictions are expected this week to accommodate punch list items in connection with work on the Downtown Crossing.

Overnight closures scheduled Monday, February 20*

  • Ramp from Muhammad Ali Boulevard/Liberty Street to I-65 North
  • Ramp from I-64 East to Story Avenue
  • One lane of I-71 North near Frankfort Avenue

 

Overnight closures scheduled Monday, February 20 and Tuesday, February 21*

  • Ramp from I-64 East to I-65 South
  • Ramp from I-71 South to I-65 South
  • Ramp from I-65 South to Jefferson Street

 

Overnight closure scheduled Wednesday, February 22*

  • I-64 West, reduced to one lane from Mellwood Avenue to Story Avenue

 

Weekend closures scheduled for Friday, February 24-Monday, February 27

  • Ramp from I-64 East to I-65 South
  • Ramp from I-71 South to I-65 South
  • Ramp from I-65 South to Jefferson Street
  • Two lanes of I-65 South from Kennedy Bridge to Jefferson Street ramp

The weekend closures are scheduled to begin around 9 p.m. Friday and end by 5 a.m. Monday.

 

*Overnight closures are scheduled to begin around 9 p.m. and end by 5 a.m. Signed detours are in place during full closures.

 

The actual starting date and duration for the work may be adjusted if inclement weather or other unforeseen activities occur. Also, given the aggressive overall construction schedule for the project, Walsh DBT may shift work schedules when opportunities arise. Find all of the latest traffic information at www.kyinbridges.com.

 